Saturday, 7 March 2015

Week 2: Brickwork finished (Tues)

I have lost track a bit of what was done on each day this past week. They finished off the brickwork at the start of the week, including fitting cavity trays. They had to grind out all of the old pointing and repointed it, then on Thursday they started preparing the roof (securing the timbers with straps). They fitted the cavity closers so our doors can go in. They have also cut a hole for the vent pipe through the roof.

On Saturday the groundworkers came in and dug the soakaway, and fitted a gulley for the kitchen sink waste.